The Xi'an Power Supply Bureau was originally scheduled to expand capacity of No. 1 main transformer in Chang’an West Substation from 0:00 on February 19 to 20:00 on February 24, and the capacity of the No. 1 main transformer after replacement would be increased from 31,500 KVA to 50,000. KVA. According to the original reconstruction plan, about 17,000 households in Chang’an District will have power restrictions.
From 0:00 on February 19th, after the power supply department worked continuously for four days and nights, at 18:00 on February 22, the replacement of the main transformer of 110 kV Chang Anxi No. 1 was completed, and the normal power supply was resumed, which was better than the public commitment to the construction period. 49 hours.
The reporter learned from the Xi'an Power Supply Bureau yesterday that with the resumption of operation of the 110 kV Chang Anxi No. 1 main transformer into the Xi’an power grid, the power supply of about 17,000 consumers in the Chang’an District has returned to normal.